Evaluation of the Factors Influencing Time and Cost Overruns in Telecom Tower Construction in Ghana
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Civil and Environmental Research
Abstract
This paper, sought to empirically evaluate the factors influencing time and cost overruns of the telecom tower
construction projects in Ghana. It involved a cross-sectional survey that used a self-administered structured
questionnaire administered to sixty seven respondents of telecom tower construction professionals. The study
found 15 major factors influencing time overruns and 14 major factors causing cost overruns in telecom tower
construction projects. It also revealed that telecom tower construction projects executed between 1992 and 2011
experienced as much as 82% time overruns, and the cost of the projects increased by 50%. The paper contributes
to the general body of knowledge in the area of project management particularly in Ghana’s construction
industry. Recommendations are also made for clients, contractors and consultants to alleviate delays in the
construction of telecom tower construction projects
Description
Citation
Danso, H., & Antwi, K. J. (2012). Evaluation of the factors influencing time and cost overruns in telecom tower construction in Ghana.